2014 Volusia County Artificial Reef Deposits

Site 1 N deposit added   10/14/14

           
Site 13 North 10/3/14      
 
      Site 13 North  10/3/14 Deposit          

On 8/24/14 a deposit was made on the ESE part of Site 7 at 2901.079'N, 8040.715'W. A barge load of 360 tons of clean concrete culverts was deposited . The height of the deposit is approximately 11 feet. The depth  is approximately 60 feet.

On 8/30/14 a deposit was made on the NW part of Site 2 at 2909.622'N, 8040.959'W. A barge load of 425 tons of clean concrete culverts and structures were deposited. The height of the deposit is approximately 14 feet. The depth  is approximately 76 feet.

On 9/1/14 a deposit was made on the NNE part of Site 12 at 2912.125'N, 8046.249'W. A barge load of 340 tons of clean concrete culverts and structures were deposited. The height of the deposit is approximately 9 feet. The depth  is approximately 80 feet.

On 9/3/14 a deposit was made on the NNE part of Site 13 at 2910.466'N, 8041.060'W. A barge load of 350 tons of clean concrete culverts and structures were deposited. The height of the deposit is approximately 15 feet. The depth  is approximately 76 feet.

On 9/5/14 a deposit was made on the SE part of Site 12 at 2909.846'N, 8041.030'W. A barge load of 360 tons of clean concrete culverts and structures were deposited. The height of the deposit is approximately 11 feet. The depth  is approximately 76 feet.

On 9/7/14 a deposit was made on the SW part of Site 10 at 2921.169'N, 8050.076'W. A barge load of 360 tons of clean concrete culverts and utility poles were deposited. The height of the deposit is approximatey 13 feet. The depth  is approximately 68 feet.

On 9/9/14 a deposit was made on the SE part of Site 10 at 2921.346'N, 8049.459'W. A barge load of 350 tons of clean concrete culverts was deposited. The height of the deposit is approximately 10 feet. The depth  is approximately 63 feet.

On 9/14/14 a deposit was made on the North  part of Site 1 at 2907.396'N, 8041.716' W. A barge load of 350 tons of clean concrete and culverts were deposited. The height of the deposit is approximately 8 feet. The depth  is approximately 63 feet.

On 9/16/14 a deposit was made on the Northern  part of Site 4 at 2919.526'N, 8041.716'W. A barge load of 350 tons of clean concrete culverts and concrete  was deposited. The height of the deposit is approximately 9 feet. The depth  is approximately 76 feet.

On 9/19/14 a deposit was made on the Western  part of Site 3 at 2911.653'N, 8045.070'W. A barge load of 350 tons of clean concrete culverts and utility  poles  were deposited. The height of the deposit is approximately 10 feet. The depth  is approximately 75 feet.

On 9/22/14 a deposit was made on the SSE part of Site 12 at 2911.587'N, 8046.192'W. A barge load of 300 tons of clean concrete culverts,structures and utility poles were deposited. The height of the deposit is approximately 12 feet. The depth  is approximately 75 feet.

On 9/29/14 a deposit was made on the WNW   part of Site 5 at 2907.360'N, 8048.555'W. A barge load of 461 tons of clean concrete culverts structures and utility poles were deposited. The height of the deposit is approximately 12 feet. The depth  is approximately 76 feet.

On 10/01/14 a deposit was made on the SSE  part of Site 3 at 2911.398'N, 8044.552'W. A barge load of 300 tons of clean concrete culverts, structures, utility poles, and parking strips were deposited. The height of the deposit is approximately 10 feet. The depth  is approximately 80 feet.

On 10/03/14 a deposit was made on the Northern  part of Site 13 at 2910.466'N, 8041.378'W. A barge load of 325 tons of clean concrete culverts, structures, utility poles, and parking stops were deposited. The height of the deposit is approximately 9 feet. The depth  is approximately 76 feet.


                                                                                                                             Home